Road resurfacing: A547, Conway Road, Llandudno Junction
Work starts: 18 November 2024
Work finishes: 4 December 2024 (weather depending)
What is happening?
We are resurfacing part of Conway Road A547 in Llandudno Junction, from the mini roundabout at Ferndale Road to the junction with Penrhos Avenue.
Our contractors will be doing most of this work during the day from 7.30am to 5.30pm, with a convoy system to escort traffic through the site.
Laying the new surface will take place at night from 6pm to 2am on Thursday 28 and Friday 29 November. Side roads will be closed briefly during this work and there may be delays on the main road.
Will it affect parking?
Yes - there will be no parking on affected sections while we do this work. There will be access for pedestrians at all times.
Will it affect deliveries?
We want to minimise disruption to your operations. If you will be expecting deliveries during the time our contractors are working, please let us know the days and times of the deliveries. You can do this by email to erf@conwy.gov.uk . Please give us as much notice as you can so we can try to make appropriate arrangements.
What is resurfacing?
Step 1 - remove the existing surface (this is called planing)
Step 2 – Adjust or replace the ironwork, manholes & drainage gullies
Step 3 - clean the surface with a mechanical sweeper
Step 4 - lay a bond coating, to make sure the new surface sticks
Step 5 - lay the new surface
Step 6 - compact and level the new surface with rollers
Step 7 - repaint the road markings
Resurfacing can be a noisy and dusty process, and we are sorry for the inconvenience this might cause. The new road surface will provide a smoother, quieter ride and will be a long lasting benefit to the community.
Questions?
If you need more information, please contact the Environment, Roads & Facilities Advice Team on erf@conwy.gov.uk or call 01492 575337.