Road resurfacing: St Asaph Avenue, Kinmel Bay
Work starts: Monday 15 January 2024 (weather permitting)
Work finishes: Friday 02 February 2024 (weather permitting)
What is happening?
We are resurfacing St Asaph Avenue, from Cader Avenue to Tir Llwyd Enterprise Park roundabout. As part of this work, we are removing the mini roundabouts and adding Give Way road markings to the side road junctions.
Our contractors will be working in the evening and at night, between 6pm and 2am, to minimise traffic disruption. This section of St Asaph Avenue will be closed at these times.
Our contractors will make every effort to carry out the noisier work earlier in the night.
Please speak to the traffic management contractor on site to discuss if and when you can get vehicle access. There will be access for pedestrians at all times.
Will it affect parking?
Yes - there will be no parking on affected sections while we do this work.
What is resurfacing?
Step 1 - remove the existing surface (this is called planing)
Step 2 – Adjust or replace the ironwork, manholes & drainage gullies
Step 3 - clean the surface with a mechanical sweeper
Step 4 - lay a bond coating, to make sure the new surface sticks
Step 5 - lay the new surface
Step 6 - compact and level the new surface with rollers
Step 7 - repaint the road markings
Resurfacing is a noisy and dusty process, and we are sorry for the inconvenience this might cause. The new road surface will provide a smoother, quieter ride and will be a long lasting benefit to the community.
Questions?
If you need more information, please contact the Environment, Roads & Facilities Advice Team on erf@conwy.gov.uk or call 01492 575337.
Thank you for your patience while we carry out this work.
Posted on 09/01/2024